Construction update Fryske Mar
The work is proceeding according to plan. The site has been cleared: old paving, cables and pipes have been removed and the vegetation has been cleared. Before the end of this year, the ditches will be dug out and the waterways deepened.
In January, construction of the underground infrastructure (sewers, electricity, water) will commence. From February onwards, eight homes will be installed in the park each month.
In June 2026, the first 24 homes will be ready for rental, fully connected and equipped with landscaped gardens and complete interiors.
Construction update Recreation Park Oysterduinen
Work on phases 2 and 3 is proceeding according to plan. Underground containers will be installed at the entrance for proper waste disposal.
At the rear of the resort (houses 39-42), concrete retaining walls will be installed to maintain the ground level and prevent subsidence of the gardens. Once this is complete, work will continue towards the long side of phase 3.
In phase 2, the groundwork will be completed at the end of this month, after which the construction of the paths can begin. We aim to have the grass behind the houses in place before Christmas.
The last houses will be installed on 18 December. After completion and technical inspections, the handover will follow.