November 2026 – Discover the latest developments at our resorts

Construction update: Fryske Mar

The park will be renamed to De Wetterhoun, a distinctive Frisian identity that blends in with the surrounding area. On the site itself, too, further progress has been made towards creating a fully-fledged park.

Site development and housing construction

  • Roads and waste facilities: the base layer of tarmac has been laid throughout the park, giving the road network a clear shape. In addition, underground waste containers for glass, PMD, paper/cardboard and general waste have been installed.
  • Progress on house placement: on 12 November, houses 4, 22, 25, and 38 were placed on their plots. The next delivery is scheduled for 26 November (properties 32, 44, 45, and 48), meaning that by the end of November, around half of all the properties in the estate will be in place. The homes in batch 6 are now under construction.
  • Last remaining properties: the majority of the development has been sold and sales are nearing completion. There are still a few holiday homes available for those interested.

A new look and improved service

  • Meet the park manager: Since October, Sanne has been the main point of contact at the park for guests and owners. She focuses on day-to-day operations and the guest experience, whilst Bert Hofman remains responsible for technical management.
  • Customer portal under development: to provide owners with even clearer information, a central customer portal is currently being tested. Once this is ready for use, you can track the progress of your property here and view information about service and warranty.
Fryske Mar Construction Update

Huis ter Heide construction update

Installation of underground utility services

Over the past few months, significant progress has been made at Huis ter Heide with the installation of underground utility networks, including the sewerage system, drinking water pipes, and fibre-optic cables. This has created a solid foundation for the further development of the park’s above-ground layout. From mid-November until the start of January, the network operator will be finalising the electricity infrastructure at the park. 

Next steps towards placement

  • Homes ready: the first homes are now ready at the builder’s site.
  • Preparing park roads: as soon as the network operator is ready, the roads will be graded and given an initial layer of semi-paved surfacing, to make them suitable for heavy goods vehicles.
  • New installation date: the first homes will be installed once the roadworks have been completed. As soon as the network operator has completed the work and there is more certainty about the exact date, a further update will follow.
Huis ter Heide construction update